    Monarch Running Total

    MTEUser _

      I am currently using Monarch Pro 11.  On this report, I want to move the Priority Date of ONLY the Mfg. Orders up 30 days, recalculate the Expected Avail based on that new date and determine when the Expected Avail goes below 1.  In the example below, M-M2870385 would now have a Priority Date of 3/30/16 moving it before P-555896 and making the Expected Avail on 3/31/16 -30.  If it can be done, I'm thinking it will involve multiple exports but I'm stumped on where to start with this. Any suggestions will be greatly appreciated!